Production Order Release
*Releasing production order means giving the green signal for production
*order can release
- manually
- automatically
- collectivelly
Production Order Release - Manual - Header level T code - Co02
Goto Co02 -> click the Release button (green colour flag) ->save
Result : you can see the status changed to REL
Production Order Release - Manual - Individual Operation wise T code - Co02
Goto Co02 -> click operations -> select the relevant operation -> click on Release operation button-> save
Result : under information you can see status as PREL (partially released)
Production Order Release - Automatically
Once created the production order Co01 it will automatically released.
Config : SPRO -> Production -> shop Floor Control -> Master Data -> Define Production Order ->Scheduling Profile -> Enter Plant ->Select the relevent line -> Details -> Tick Release on Creation under Automatic Actions
Then Goto Materail on MM02 -> Work Scheduling Tab -> Production Schedule Profile -> give the selected profile -> Save
Production Order Release - Collective T code -COHV
Goto COHV ->Navigate to Mass Processing Production Order Screen -> Tick Production Order ->
On selecetion screen enter Material and Plant -> Selection screen select System Status as "REL" and tick on exclude -> Goto Mass Processing Tab -> Select function as Release -> Execute
Then all orders will appear -> Select all -> Go to Mass processing -> Execute
Result : Goto MD04 -> all orders for selected materails has been released